- Home
- Our Community
- For Residents
- Construction Updates
- Street Improvement Program
Street Improvement Program
Roselle has 74 miles of streets that are maintained by the Village through our annual Street Improvement Program. The annual Street Improvement Program includes resurfacing, patching, and reconstruction of Village streets, including work on storm sewers, sidewalks, and curbs when warranted.
The Village prioritizes streets for the Street Improvement Program based on the most recent 5-year pavement study and road conditions. Streets are also prioritized for improvement when water main replacements are needed in the same location. This way, we get all major construction done at the same time to reduce any burden on residents. Below are construction updates for this year’s program and a list of this year’s streets. You can view a PDF version of the 2023 improvement map by clicking here.
Construction Updates
Construction schedules change frequently due to weather, supply issues, etc. Check this page for the most up-to-date information on Street Improvement Program projects.
Week of September 25
W. Maple Ave. | The contractor is expected to begin concrete removal and replacement on September 29th on the north side of Maple Ave (Roselle Rd to Hill St) Notices will be passed out to residents whose driveway is impacted by removals. |
Week of September 18
Phase 2 Streets | The contractor is expected to begin concrete removal and replacement on September 20th on W Ardmore Ave, Willow St (Pine to Maple) and the south side of Maple Ave (Roselle Rd to Hill St) Notices will be passed out to residents whose driveway is impacted by removals. |
Week of August 7
ALL Phase 1 Streets | The contractor will be placing the first lift of hot-mix aspahlt on the street tomorrow August 10th. In preperation for the placement of the new aspahlt the contractor will be placing a tack coat/oil early in the morning. The tack coat dries within a few hours. Fresh oil signs will be in place. Please drive on the tack coat slowly so it does not track. |
Week of July 31
ALL Phase 1 Streets | Resurfacing expected to begin on Monday August 7th. Please do not park in the street unless notified to do otherwise. The substantial completion of the phase 1 streets has been extended to August 31. |
Week of July 17
Parkview Neighborhood | Contractor will continue stage 3 replacement starting Monday, July 17. Please view the notification letter for more information: |
Week of July 10
Parkview Neighborhood | Stage 3 concrete removals are scheduled for the week of July 17th. |
ALL Phase 1 Streets | Resurfacing is tentatively scheduled to begin the week of August 14th. The substantial completion of the phase 1 streets has been extended to August 31st. |
Week of June 26
Parkview Neighborhood | Stage 2 concrete removal and replacement is completed, and residents may resume parking in their driveways. Due to the 4th of July the contractor has postponed stage 3 until the week of July 10th. |
Week of June 19
Parkview Neighborhood | Stage 1 concrete removal and replacement completed. Residents may park back in their driveways once the barricade is moved. Notification: Stage 1 Complete - 6/16/23 Stage 2 concrete removals expected to start on June 19. Contractor will pass out 24 hour notification if driveway access is impacted by removals. |
Indian Hill Dr, E Ardmore Ave, S Prospect St | Concrete removals expected to finish the week of June 19. Contractor will pass out 24 hour notification if driveway access is impacted by removals |
Resident Information:
- Resident Information Bulletin - April 21, 2023
- Resident Information Bulletin - April 25, 2023
- Resident Information Bulletin - June 7, 2023
Streets Included in the 2023 Street Improvement Program:
- E Ardmore Ave. from Roselle Rd. to S Prospect St.
- Hale Ln. from Indian Hill to east Village limit
- Indian Hill Dr. from Nerge Rd. to south end
- W Maple Ave. from Roselle Rd. to Valley Rd.
- Morningside Ct. from Morningside Dr. to west end
- Morningside Dr. from Rosner Dr. to Lawrence Ave.
- S Prospect St. from Woodworth Pl. to E Pine Ave.
- Rosner Dr. from Terry Dr. to Morningside Dr.
- Terry Ct. from Terry Dr. to east end
- Terry Dr. from Lawrence Ave. to Rosner Dr.
- Willow St. from W Maple Ave. to W Pine St